QPR Knowledge Base 2017.1

QPR Metrics Server Performance Improvements (306770)

QPR Metrics Server Performance Improvements (306770)

Previous topic Next topic No directory for this topic  

QPR Metrics Server Performance Improvements (306770)

Previous topic Next topic Topic directory requires JavaScript Mail us feedback on this topic!  

It is now possible to disable the scheduled tasks (integration tasks, time dependent calculation, and period level automation) so that they are not run in QPR Metrics server. The functionality is controlled by the "SchedulerEnable" .ini key in the "QPR_Servers.ini" file. The setting makes it possible to start QPR Metrics server even when there are broken scheduled tasks. The functionality is also useful when investigating a big QPR Metrics database that contains a large number of scheduled integration tasks that don't necessarily need to be run when investigating some particular model.